The Interconnection Agreement
Generation of Less Than 20 MW
If you have completed both your System Impact and Facility studies – or have met the eligibility requirements through the Fast Track Process – then you are ready to execute the Interconnection Agreement or begin negotiations regarding the Interconnection Agreement. A draft of the Small Generation Interconnection Agreement (Appendix 6) will be provided to you once the Facility Study has been completed.
TEP will provide you with an Interconnection Agreement. You have 30 calendar days to sign and return the Interconnection Agreement. Once both parties sign the agreement, the interconnection project will proceed.
WHAT YOU DO
- Execute Interconnection Agreement.
WHAT TEP DOES
- Issue a draft of the Interconnection Agreement (SGIA) to you upon completion of the Facilities Study or if you have met the eligibility requirements through the Fast Track Process.
Contact us with questions and requests:
Generator and Transmission
Interconnection Requests and Questions