Fast Track Process

The Fast Track Process is available to applicants proposing to interconnect Small Generating Facilities of less than 2 MW that meet the codes, standards and certification requirements of Attachment 3 and Attachment 4 of the SGIP or have been determined by TEP that the proposed facility is safe to operate.

WHAT YOU DO

  • Complete Attachment 2 of the SGIP
    • Under the “Generation Interconnection” folder, select “SGIP Attachment 2 Interconnection Request” and the file will download
  • Submit your $1,000 deposit to TEP
  • Provide site control for your project

WHAT TEP DOES

  • Reviews your application, acknowledges the processing fee received and verifies site control
  • Notifies you if your proposed interconnection request meets eligibility requirements. If it does, you may proceed directly to the Interconnections Agreement.
  • Provides you with an Interconnection Agreement within 5 business days after our determination.
  • If your project does not meet eligibility requirements, you will need to complete the Full Study Process.